The Party Wall etc Act 1996
The Party Wall etc Act 1996 or Party Wall Agreement provides a framework for preventing and resolving disputes in relation to party walls, boundary walls and excavations near neighbouring buildings. A building owner proposing to start work covered by the Act must give adjoining owners notice of their intentions in the way set down in the Act.
What is the Party Wall Act?
The Party Wall etc Act 1996 provides a procedure to follow when building work involves:
- Cutting into a party wall,
- Excavations close to neighbouring buildings,
- New walls at boundaries.
The Act permits owners to carry out certain specific works whilst at the same time protecting the interests of anyone who might be affected by that work. It makes sure property owners notify their neighbours in advance of certain proposed works and provides a mechanism for resolving disputes and enabling works to proceed.
The Party Wall etc Act 1996
What is a party wall?
a). a wall that stands on the lands of 2 (or more) owners and forms part of a building – this wall can be part of one building only or separate buildings belonging to different owners
b). a wall that stands on the lands of 2 owners but does not form part of a building, such as a garden wall but not including timber fences
c). a wall that is on one owner’s land but is used by 2 (or more) owners to separate their buildings
The Act also uses the expression ‘party structure’. This could be a wall or floor partition or other structure separating buildings or parts of buildings in different ownership, such as in flats.
Notices
It is essential to include the correct details on a notice as, if they are deemed invalid, then any subsequent actions are also invalid.
Responses To Notices
a). To consent to the works going ahead as described. A consenting Adjoining Owner retains all rights under the Act including the right to dissent later in the process.
b). To dissent and appoint a surveyor to check the plans, structural implications and agree the terms of an award (the document that sets out the terms under which work can begin).
c). To dissent and appoint us as an ‘agreed’ surveyor. As point two above but we would act on behalf of both parties.
If the Adjoining Owner does not respond within 14 days then a deemed dispute is said to have occurred and the person carrying out the work must appoint a surveyor to act on the Adjoining Owners behalf.
Resolving Disputes
How Long Can My Neighbours Take To Respond?
Generally, the building owner who is carrying out the work pays for all expenses, this will include the surveyors fees for both Building Owner and Adjoining Owner.
If you want expert advice contact us on 0208 191 7747 or email to office@whiteandlloyd.com
Related Information
Are you a Building Owner?
FREQUENTLY ASKED QUESTIONS
Are you an Adjoining Owner?
Working With Us
Send us a Message
Head Office
Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747
London Office
Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213