chris, Author at White & Lloyd Building Surveyors Thu, 12 Dec 2019 13:58:09 +0000 en-GB hourly 1 https://wordpress.org/?v=6.1.7 https://www.wlbuildingsurveyors.co.uk/wp-content/uploads/2019/12/cropped-favicon-32x32.png chris, Author at White & Lloyd 32 32 How Much Does a Party Wall Agreement Cost? https://www.wlbuildingsurveyors.co.uk/2019/06/how-much-is-a-party-wall-agreement/ Thu, 06 Jun 2019 10:01:49 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208256 The post How Much Does a Party Wall Agreement Cost? appeared first on White & Lloyd.

]]>

How Much Does a Party Wall Agreement cost?

The cost of a party wall agreement will depend on the type of project being carried out and the quality of the design information in place. The cost is determined by the surveyors hourly rate and the amount of time they are required to spend to put the awards in place. Most party wall surveyors charge a fixed hourly rate for all party wall matters, this will typically range from £120 – £250 per hour.

THE EXPECTED HOURS AND COSTS FOR A PARTY WALL AGREEMENT WOULD BE:

TWO APPOINTED SURVEYORS
Project Type Building Owners SurveyorAdjoining Owners SurveyorTotal Cost
(per agreement)
Loft Conversion6 to 8 hours
£900 to £1200
6 to 8 hours
£900 to £1200
£1800 to £2400
Extension8 to 10 hours
£1200 to £1500
8 to 10 hours
£1200 to £1500
£2400 to £3000
New Build10 to 12 hours
£1500 to £1800
10 to 12 hours
£1500 to £1800
£3000 to £3600
Basement12 to 18 hours
£1800 to £2700
12 to 18 hours
£1800 to £2700
£3600 to £5400

Assumes an hourly rate of £150 per hour.

AGREED SURVEYOR
Project Type Agreed SurveyorTotal Cost
(per agreement)
Loft Conversion6 to 8 hours
£900 to £1200
Extension8 to 10 hours

£1200 to £1500
New Build10 to 12 hours

£1500 to £1800
Basement12 to 18 hours
£1800 to £2700

Assumes an hourly rate of £150 per hour.

The number of hours involved will depend on:
  1. The quality and completeness of the design information
  2. The complexity of the project
  3. The level of risk of damage on the adjoining property
  4. The quality and completeness of the draft award and schedule of condition prepared by the building owners surveyor
  5. Whether a matter has had to be referred to the Third Surveyor

It should be noted that there is no upper limit on the costs, as long as fees are reasonable.

Once the awards are agreed the surveyors will apportion the “reasonable” fees. In usual circumstances fees will be payable by the building owner.

WHAT IF SURVEYORS FEES ARE NOT REASONABLE?
It falls to the building owners surveyor to determine whether or not the adjoining owners surveyors fees are reasonable. If there is concern then surveyors will review timesheets and ensure that all time spent is within the surveyors remit and in direct relation to the work being carried out.

If there is concern over the fees then the matter may be referred to the third surveyor for a determination.

If an award is served containing unreasonable fees then it may be appealed, in the County Court, within 14 days of being served.

This action can incur additional cost, we always recommend that specialist advice is sought before referring a matter to the third surveyor or appealing an award.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post How Much Does a Party Wall Agreement Cost? appeared first on White & Lloyd.

]]>
WHEN IS A PARTY WALL AGREEMENT REQUIRED? https://www.wlbuildingsurveyors.co.uk/2019/06/when-is-a-party-wall-agreement-required/ Thu, 06 Jun 2019 09:41:04 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208251 The post WHEN IS A PARTY WALL AGREEMENT REQUIRED? appeared first on White & Lloyd.

]]>

WHEN IS A PARTY WALL AGREEMENT REQUIRED?

 

The Party Wall etc Act 1996 provides a procedure to follow when building work is likely to impact the adjoining properties. Work involving alterations to a party wall, excavations close to neighbouring buildings, or new walls built on or astride a boundary line will fall under The Party Wall Act, meaning a notice needs to be served on the adjoining owners before work can start.

Where the adjoining owner receives a notice but does not ‘agree’ in writing to the works, a surveyor or surveyors will need to produce an agreement (usually called an Award) to set out the terms under which the work can proceed.

What is covered by the Act?

There are certain items of work that you can only be done after notifying the adjoining owners and either receiving written agreement of the neighbour or with a Party Wall Award prepared by a surveyor/s.

Notifiable works include (but are not limited to):

  • cutting into a wall to take the bearing of a beam, for example for a loft conversion
  • inserting a damp proof course, even if only to your own side of a party wall
  • raising a party wall and, if necessary, cutting off any objects preventing this from happening
  • demolishing and rebuilding a party wall
  • underpinning a party wall or part of a party wall
  • weathering the junction of adjoining walls or buildings by cutting a flashing into an adjoining building
  • excavating foundations within three metres of a neighbour’s structure and lower than its foundations
  • excavating foundations within six metres of a neighbour’s structure and below a line drawn down at 45° from the bottom of its foundations.

Notices are also required if it is proposed to build a new wall on the line of junction (boundary line). A party wall surveyor will usually be able to confirm which work is notifiable and advice the notice period and type of notice required.

WHICH WORK IS NOT COVERED BY THE ACT?

The Act relates only to certain specific types of work and is permissive in nature. It should not be seen as a method of objecting to or preventing works and it is not intended to be applied to minor jobs that do not affect the structural integrity or loading of a party wall.

It is generally agreed that works such as fixing plug sockets, screwing in shelving or replastering walls are minor works and do not require a notice.

Notices

The workings of the Act are always instigated by the of issuing notices. This is the first stage of the process and, without the issue of valid notices, no further action can be taken under the provision of the Act.

Written notice must be served on adjoining owners at least two months before starting any party wall works (one month for works to the line of junction or excavations). All adjoining owners must be served a notice and there are likely to be instances where there is more than one adjoining property and more than one owner of each property (ie: if the adjoining property is split into flats and owned on a leasehold basis, notices will be required to both leaseholder and freeholder of all flats affected by the works). Works to a party wall, or those affecting a ceiling or floor, will also require a notice to adjoining owners living above or below.

It is essential to include the correct details on a notice as, if they are deemed invalid, then any subsequent actions are also invalid. If you are in any doubt as to who should receive a notice or what it should include then you should seek advice from a party wall surveyor – most will be happy to help free of charge.

Responses To Notices

On receipt of a notice, an adjoining owner has three possible courses of action:

  1. To consent to the works going ahead as described. A consenting Adjoining Owner retains all rights under the Act including the right to appoint a surveyor later in the process if there is a dispute at that stage.
  2. To dissent and appoint a surveyor. The Act allows the Owners to concur in the appointment of a single ‘Agreed’ surveyor or appoint their own separate surveyor.
  3. Issue a counter notice to set out certain conditions required for the benefit of the Adjoining Owner. The Counter Notice should set out what additional or modified work the Adjoining Owner would like to be included for his benefit

In most cases, if the adjoining does not respond within 14 days then a deemed dispute is said to have occurred and the person carrying out the work must appoint a surveyor to act on the adjoining owners behalf.

If adjoining owners provide written consent to the works as set out within the notices, then there is no dispute to resolve and no further need for a party wall agreement. Assuming work proceeds as detailed within the notice and no damage is caused, then no further involvement is necessary.

THE PARTY WALL AGREEMENT (AWARD)

If adjoining owners dissent to the works (or if no response is received and a deemed dissent has arisen) then a dispute has occurred which must be resolved under the requirements of Section 10 of The Act. It is worth reiterating that the Act is one of enablement, it is not there to prevent works from taking place and it offers a route to end disputes at every stage. Where written agreement is not given, the solution the Act provides is for both parties to appoint an ‘agreed surveyor’ who will act impartially or for each owner to appoint a surveyor who in turn appoint a third surveyor. The surveyors then work together to agree the terms under which work may proceed. The surveyor(s) will review the plans, notices and structural details of the works and, after considering the impact of the works, will draw up an agreement which sets out the terms under which work can be carried out (the Award).

The award will usually record the condition of the relevant part of adjoining property before work begins (this is not a requirement under the Act but is considered good practice and is duly provided by most good surveyors). The award may also grant access to both properties so that the works can be safely carried out and the surveyor/s can inspect work in progress.

Generally, the building owner who started the work pays for all expenses of work and the reasonable costs incurred by all parties as a result, this will include the surveyors fees for both Building Owner and Adjoining Owner.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post WHEN IS A PARTY WALL AGREEMENT REQUIRED? appeared first on White & Lloyd.

]]>
How To Reduce Party Wall Costs https://www.wlbuildingsurveyors.co.uk/2019/06/how-to-reduce-party-wall-costs/ Thu, 06 Jun 2019 09:38:26 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208245 The post How To Reduce Party Wall Costs appeared first on White & Lloyd.

]]>

How To Reduce Party Wall Costs

The cost of a party wall agreement will depend on the type of project being carried out, the quality of the design information in place and the number of surveyors involved. The cost is determined by the surveyors hourly rate and the amount of time they are required to spend to put the awards in place. The cost of the party wall process will be reduced if surveyors hours can be kept to a minimum.

How To Reduce Party Wall Costs

DISCUSS THE WORKS WITH THE ADJOINING OWNERS BEFORE SERVING NOTICE:

The easiest, quickest and cheapest way to reach a party wall agreement is to receive the consent of the adjoining owners.

If a notice has been served, and the adjoining owners provide a written consent, then this is the end of the process.

We strongly recommend that building owners discuss their works with the adjoining owners, outlining the specific aspects that may affect them.

Adjoining owners are far more likely to consent if they understand the works and the reason for serving notice.

It is worth bearing in mind that the two parties (building owner and adjoining owner) are free to reach any agreement they want. It is perfectly valid for an adjoining owner to consent on the basis that the building owners provides something in return. 

This could be:

  • A survey of the adjoining property
  • A promise to repair the fence
  • A bottle of wine
  • A future consent to future work by the adjoining owner
  • Anything that both parties decide
USE AN AGREED SURVEYOR WHERE POSSIBLE
Less complex jobs are most efficiently dealt with by an agreed surveyor (where one surveyor acts for both parties). This route needs the agreement of all parties (both property owners and the surveyor in question) but it usually represents the quickest and most cost effective means of putting a party wall agreement in place.

The agreed surveyor route means the building owner is liable for one set of fees rather than two, so it is worth discussing with the adjoining owner to see if this is a viable option.

APPOINT A COMPETENT DESIGN TEAM
It is worth checking the competency and experience of the design team before appointing them. Incomplete or poorly considered designs can delay the party wall process and add a significant cost.

Competent architects and engineers should be aware of the information that is required for the party wall agreement. If there is any doubt then you should pass the design information to a party wall surveyor for comments on its adequacy before starting the party wall process.

APPOINT A COMPETENT PARTY WALL SURVEYOR

Costs will be higher if the adjoining owners surveyor is spending significant amounts of time correcting mistakes or poorly presented information form the building owners surveyor.

The building owners surveyor is usually responsible for:

  1. Preparing and sending notices
  2. Preparing the schedule of condition
  3. Preparing the draft award
  4. Reviewing design information before sending on
  5. Preparing the document register

If the one surveyor is spending time correcting mistakes made by the other then costs will be higher.

It is therefore worth checking the accreditation and experience of a surveyor before appointing them.

Do not be put off by a higher hourly rate. This will usually signify greater competency and experience so the process should go through quicker and smoother, meaning a lower total cost.

BE PREPARED TO COMPROMISE
A party wall agreement often turns into a negotiation, whereby the adjoining owners may have specific concerns they would like addressed (often revolving around hours of work, location of scaffolding, the use of protective hoarding…etc).

Often the cost of enforcing a particular point can outweigh the cost of agreeing to it, so a flexible and conciliatory approach can be an effective way of minimising costs.

WHAT IF SURVEYORS FEES ARE NOT REASONABLE?
It falls to the building owners surveyor to determine whether or not the adjoining owners surveyors fees are reasonable. If there is concern then surveyors will review timesheets and ensure that all time spent is within the surveyors remit and in direct relation to the work being carried out.

If there is concern over the fees then the matter may be referred to the third surveyor for a determination.

If an award is served containing unreasonable fees then it may be appealed, in the County Court, within 14 days of being served.

This action can incur additional cost and we always recommend that specialist advice is sought before referring a matter to the third surveyor or appealing an award.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post How To Reduce Party Wall Costs appeared first on White & Lloyd.

]]>
Is Your Neighbour Carrying Out Building Work? https://www.wlbuildingsurveyors.co.uk/2019/01/is-your-neighbour-carrying-out-building-work/ Wed, 16 Jan 2019 13:41:30 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208013 The post Is Your Neighbour Carrying Out Building Work? appeared first on White & Lloyd.

]]>

Is Your Neighbour Carrying Out Building Work?

Michael White C.Build.E FCABE FFPWS, one of our senior surveyors, offers some information and advice to “Adjoining Owners”, if neighbour carrying out building work

Advice To Adjoining Owners

We understand it can be a stressful time when there are extensive building works going on next door. We also realise The Party Wall Act can be a daunting prospect to those that have not experienced the process before. Michael White C.Build.E FCABE FFPWS, one of our senior surveyors, offers some information and advice to “Adjoining Owners”….

Is Your Neighbour Carrying Out Building Work?

An adjoining owner is defined in The Party Wall etc Act 1996 as: “any owner… of buildings, storeys, or room adjoining those of the building owner”.

It may be that you are regarded as an adjoining owner if your property is within 3m (and sometimes 6m) of the building owners’ property.

The building owner is the owner of the property where works are to be carried out.

When building owners plan to carry out works that might affect the structure of neighbouring properties, The Party Wall Act is there to protect all parties and, primarily, the wall itself.

The Act requires formal Notice to be served on all adjoining owners before work commences. If you have received a Party Wall Notice or, worse, if works have started without a Notice, you may find the following advice helpful:

1. If works have started and you haven't received a Notice
If works have started and you haven’t received a Notice, you should speak to your neighbour in the first instance, it may be that the building works don’t require a Notice. If you are not certain, please ask us.
2. When you receive a Notice
When you receive a Notice, it will usually ask you to ‘consent’ or ‘dissent’ to the works. This may appear that you can stop the works if you wish but, in reality, it is offering you the right to have the works checked and provides protection against any damage that may occur.
3. If you 'consent'
If you ‘consent’ then the work will proceed without any checks under the Act. In the event of any damage you will be left exposed and it will be significantly harder to recover the cost of remedial work.
4. Dissent to ensure you have the protection of the Party Wall Act
We recommend adjoining owners dissent to ensure you have the protection of the Party Wall Act. It sets out the terms under which compensation may be paid and may even require the building owner to set aside an agreed sum of money in a holding account to cover any damage to the party wall or the neighbouring property.
5. If you choose to dissent
If you choose to dissent you will need to appoint a surveyor to act on your behalf. The cost of this falls on the person carrying out the work.
6. Your surveyor will then check the building plans
Your surveyor will then check the building plans and discuss any important points with you. If necessary, the surveyor will appoint a ‘checking engineer’ to check the structural aspects. It is in the best interests of both parties (and the wall itself) to ensure the work has been adequately designed.
7. surveyors are required to be impartial
Under The Act, surveyors are required to be impartial, they are working in the best interests of the wall. Your neighbour is required to pay all of the reasonable costs, so it should cost you nothing.
8. Your property will be inspected
As part of the process, your property will be inspected by the surveyor(s) and its existing condition recorded. Should any damage occur during or after the work, the Schedule of Existing Condition is used to prove it is as a result of the works.
9. The surveyor(s) will then agree the terms
The surveyor(s) will then agree the terms under which work can begin. They will also set out any precautions that might need to be taken to protect your property.
10. These terms form the Party Wall Award
These terms form the Party Wall Award, a legally binding document which is signed the surveyor(s) and issued to the property owner and the adjoining owner.
11. Your surveyor may also retain involvement
Your surveyor may also retain involvement during the works, so you can raise any issues or concerns you may have as work proceeds. A competent surveyor will have agreed within the Award that any reasonable fees incurred during the work will be met by the building owner
12. Inspection on completion
12. The properties are then inspected on completion to check for any damage. If there is damage, then you have the choice of letting their contractor put it right or taking compensation instead.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post Is Your Neighbour Carrying Out Building Work? appeared first on White & Lloyd.

]]>
The problem of rogue surveyors operating under the Party Wall Act? https://www.wlbuildingsurveyors.co.uk/2018/10/the-problem-of-rogue-surveyors-operating-under-the-party-wall-act/ Thu, 04 Oct 2018 15:44:08 +0000 http://wandl.simplecsr.com/?p=207434 The Good, The Bad & The Ugly The Party Wall Act etc 1996 allows surveyors to act under statute, providing a level of responsibility and professional duty to those that are not required to hold any qualifications, accreditations or specific competencies. Here, Michael White C.Build.E FCABE FFPWS, explores the growing issue of rogue surveyors… This […]

The post The problem of rogue surveyors operating under the Party Wall Act? appeared first on White & Lloyd.

]]>
The Good, The Bad & The Ugly

The Party Wall Act etc 1996 allows surveyors to act under statute, providing a level of responsibility and professional duty to those that are not required to hold any qualifications, accreditations or specific competencies. Here, Michael White C.Build.E FCABE FFPWS, explores the growing issue of rogue surveyors…

This is clearly a sensitive subject, and one that should be treated with care to avoid smearing the professional majority with the same murky brush as the unethical few. There is not an industry in the land that is free from people taking advantage of the vulnerable or exploiting the powers given to them. The Party Wall Act provides surveyors with the ability to override the legal rights of their neighbours. It gives the opportunity to cut into the adjoining property, to underpin it, or even to demolish and rebuild it. All actions that, under common law, would be considered as nuisance, trespass or criminal damage. It seems only correct that The Act is administered with correct amounts of care and attention and with a due regard to the rights and responsibilities of owners on both sides of the fence.

The Good

The Act has much to be admired for. It is, at its core, an enabling piece of legislation, designed to resolve disputes and provide rights to all owners. It is there to allow work to proceed rather than prevent or delay it and, when administered well, it can provide valuable assistance to the building owners wishing to build on or near the line of junction. There are numerous surveyors who could be considered as experts in the field, providing the necessary technical know how to recognise the relevant issues as well as providing the ability to implement The Act’s mechanisms to resolve technical disputes in an efficient manner.

There is also excellent guidance available on the subject. Practising surveyors and the general public can tap into resources made available by DCLG, RICS, The Faculty of Party Wall Surveyors, The Pyramus & Thisbe Club and others. Indeed, it is difficult to pinpoint a field of surveying that benefits from greater levels of assistance and advice.

The Bad

For all the good contained within The Act, it fails to insist on minimum standards of competence or qualifications of those appointed surveyors upon whose shoulders its powers are placed. The outcome is fairly inevitable: a vast majority of ethically minded and professionally competent surveyors working alongside the few that are prepared to take advantage of the opportunity to secure appointments from unsuspecting owners, create disputes and generate excessively high fees. The tactics will be familiar to all those that have experience in party wall matters: taking the best part of two weeks to respond to an email, insisting on disproportionate levels of security / checking engineering / movement monitoring / site investigations, and then the old chestnut of delaying the consent to special foundations (if taken to the extreme this consent is withheld to the point where the building owner designs the less efficient mass concrete solution which, when put to the checking engineers, is quickly replaced with the original special foundations along with all the necessary consents….. ah, those loveable rogues!).

The issue of excessive fees is one that will resonate with most building owners (and their surveyors). The wayward surveyor has become adept at delaying the start of the works to such an extent that, by the time the fees become due, the building owner is prepared to pay whatever it takes to bring an end to the whole sordid affair.

The Ugly

There are certain misdemeanors that sail way beyond the description of “bad”. The most common of which is the unethical securing of appointments. The general tactic will be familiar to most and goes something along the lines of:

  1. Scour planning sites looking for notifiable work
  2. Write to the adjoining owner to tell them their neighbour is obliged to serve notice
  3. Include a line that says “To take advantage of our FREE OF CHARGE service please sign here”
  4. Armed with a signed appointment write to the building owner to explain they must serve a notice
  5. Once formally appointed charge top rate fees for very little valuable input.

A surprisingly widespread practise that will be familiar to all those that have submitted a planning application, or lived next door to someone that has. The real problems manifest themselves later in the process when both owners find themselves with a non-communicative surveyor, prepared to put in only minimal input before demanding maximum fees. It is clear that these surveyors do not act in the best interests of their appointing owners and have no intention of doing so. It is a practice has been going on for long enough to give party wall surveyors a reputation that does not sit well alongside the high standards of the RICS and the other accrediting bodies.

The Answer?

This surveyor does not claim to hold the answers but, as with most problems, the pathway to a solution must lie among some difficult questions:

  • Does there needs to be greater regulation among party wall surveyors?
  • Is it possible to restrict to the ability to be appointed to those that can prove a level of ethics and competency?
  • Could there be any means of control over those that look to abuse the process?

The Party Wall Act is twenty years old this summer and the problem appears to be on the increase. There may be a temptation to avoid rocking the boat that provides a living, but we all have a duty to protect the integrity of the profession.

It seems, to this surveyor at least, to be high time we look to answer some difficult questions.

About the author:

Michael White has been working in the construction industry for 18 years and is a Chartered Building Engineer (C.Build.E) and a fellow of the Chartered Association of Building Engineers (FCABE). He is also a fellow of the Faculty of Party Wall Surveyors (FFPWS) and a member of the Pyramus & Thisbe Club.

Michael has a first class honours degree in Building Surveying from the University of Reading and now practices as a Party Wall Surveyor and Building Engineer. He is one of two directors at White & Lloyd Ltd, a chartered construction consultancy based in Thames Ditton, Surrey.

The practice is accredited by the Chartered Institute of Building (CIOB) and regulated by the Royal Institution of Chartered Surveyors (RICS).

We thrive on your feedback, if you have any comments or questions on the above article we would be delighted to hear from you:

Telephone: 0208 191 7747

E-mai: partywall@whiteandlloyd.com

Twitter: @whiteandlloyd

The post The problem of rogue surveyors operating under the Party Wall Act? appeared first on White & Lloyd.

]]>
How to Serve a Party Wall Notice https://www.wlbuildingsurveyors.co.uk/2018/10/how-to-serve-a-party-wall-notice/ Thu, 04 Oct 2018 15:43:45 +0000 http://wandl.simplecsr.com/?p=207432  How to serve a Party Wall Notice – What is required of a valid notice? When should they be served and to who? The Party Wall etc Act 1996 allows notices to be served by Building Owners, but it is vital that the notices contain the correct information, are served in sufficient time and to […]

The post How to Serve a Party Wall Notice appeared first on White & Lloyd.

]]>
 How to serve a Party Wall Notice – What is required of a valid notice? When should they be served and to who?

The Party Wall etc Act 1996 allows notices to be served by Building Owners, but it is vital that the notices contain the correct information, are served in sufficient time and to the correct recipients. Without a valid notice, all subsequent action under the Act may also be invalid, so it is crucial this stage is handled correctly. Our senior party wall surveyor, Michael White, explains types of work that are notifiable and what is required of a valid notice…..

The serving of valid notices is a key requirement of the Act and, without it, no further action is under the Act is possible. A notice is the starting point from which everything else follows. It is therefore crucial to ensure that notices are valid, served at the right time, to the right recipients and cover all items of the notifiable work.

Notices are required when the Building Owner proposes to carry out work under sections 1, 2 or 6 of The Act. As a result, there are 3 types of notice that may have to be served upon an adjoining owner to make them aware of intended work. The Act sets out the detail that should be included in a notice and the requirements vary slightly for each type.

Line of Junction Notice (Section 1)

Served under section 1, a Line of Junction notice covers two distinct tasks:

  1. The construction of a new wall built upto a boundary.
  2. The construction of a new wall built astride a boundary.

The notice period is one month.

The section 1 notice must indicate the Building Owners desire to build. It is also a requirement that the notice describes the intended wall. The requirements are set out in sections 1(2) and 1(5) of The Act.

If the adjoining owner does not respond to a section 1 notice relating to a neighbour’s intentions to build a new wall up to the boundary, the work can commence when the notice period has expired (note: this is in contradiction to section 2 and section 6 notices, whereby a deemed dissent occurs if the Adjoining Owner fails to respond to a notice).

The building owner may place any necessary footings and foundations (with the exception of reinforced foundations known as ‘special foundations’) under the adjoining owner’s land provided that it is necessary.

The building of a new wall astride the boundary is the only type of work covered under the Act which the adjoining owner can prevent. If the adjoining owner does not respond in writing within 14 days, the building owner will have to build the new wall entirely on his side of the boundary line. Again, the building owner may place any necessary footings and foundations (with the exception of ‘special foundations’) under the adjoining owner’s land.

Party Structure Notice (Section 2)

Party Structure Notices are served under section 3 of the act but cover works described in section 2. They cover alterations that directly affect the party wall and may include (but are not limited to) the following items of work:

  1. to underpin, thicken or raise a party structure or a party fence wall
  2. to make good, repair, or demolish and rebuild, a party structure or party fence wall
  3. to demolish a partition which separates buildings belonging to different owners
  4. to cut into a party structure for any purpose
  5. to cut away from a party wall, party fence wall, external wall or boundary wall any footing or any projecting chimney breast, jamb or flue
  6. to cut away or demolish parts of any wall or building of an adjoining owner overhanging the land of the building owner or overhanging a party wall
  7. to cut into the wall of an adjoining owner’s building in order to insert a flashing or other weather-proofing

The notice period for a section 2 notice is 2 months.

Section 3(1) sets out the information needed within the section 2 notice for it to be regarded as valid:

3(1)        (a)          the name and address of the building owner;

(b)          the nature and particulars of the proposed work including, in cases where the building owner proposes to construct special foundations, plans, sections and details of construction of the special foundations together with reasonable particulars of the loads to be carried thereby; and

(c)           the date on which the proposed work will begin.

Notice of Adjacent Excavation (Section 6)

Notices of Adjacent Excavation are concerned with works notifiable under section 6 of the Act. There are two types of excavations that are covered under section 6:

  1. Excavating within 3 metres of the adjoining building and to a depth lower than the bottom of the foundations
  2. Excavating within 6 metres of the adjoining building, if any part of that excavation intersects with a plane drawn downwards at an angle of 45 degrees from the bottom of the adjoining foundations, taken at a line level with the face of their external wall.

The notice must contain the same information as a Party Structure Notice. In addition, section 6(5) requires a statement as to whether the Building Owner proposes to underpin or otherwise strengthen or safeguard the adjoining owner’s foundations. Section 6(6) also sets out that notices must be accompanied by plans and sections showing the extent of the proposed excavation.

Serving Notices

Notices may be served in the following ways:

  1. Delivered to the Adjoining Owner(s) in person
  2. Sent via post
  3. Sent via email if the adjoining owner has confirmed a willingness to receive the notice electronically.

In instances that the name of the Adjoining Owner is not known, the notice may be addressed to “The Owner”, adding the address of the premises. In this case the notice must be served in person and hand delivered to a person on the premises. If the adjoining property is unoccupied, the notice should be fixed to a conspicuous part of the premises.

Counter Notices

Having been served a valid notice, the Adjoining Owner may serve a counter notice on the Building Owner stipulating certain conditions required for the benefit of the Adjoining Owner. The Counter Notice should set out what additional or modified work the Adjoining Owner would like to be carried out, and should be accompanied by all necessary particulars.

Section 4(3) sets out that the requirements contained within a counter notice must be complied with unless the works required would:

  1. Be injurious to the Building Owner
  2. Cause unnecessary inconvenience to the Building Owner
  3. Cause unnecessary delay in the execution of the works

A counter notice must be served within one month of the service of the original notice. If the Building Owner does not respond a counter notice within 14 days, then a dispute is deemed to have arisen and should be dealt with under the provisions of section 10.

About the author:

Michael White has been working in the construction industry for 18 years and is a Chartered Building Engineer (C.Build.E) and a fellow of the Chartered Association of Building Engineers (FCABE). He is also a fellow of the Faculty of Party Wall Surveyors (FFPWS) and a member of the Pyramus & Thisbe Club.

Michael has a first class honours degree in Building Surveying from the University of Reading and now practices as a Party Wall Surveyor and Building Engineer. He is one of two directors at White & Lloyd Ltd, a chartered construction consultancy based in Thames Ditton, Surrey.

The practice is accredited by the Chartered Institute of Building (CIOB) and regulated by the Royal Institution of Chartered Surveyors (RICS).

We thrive on your feedback, if you have any comments or questions on the above article we would be delighted to hear from you:

Telephone: 0208 191 7747

E-mai: partywall@whiteandlloyd.com

Twitter: @whiteandlloyd

 

The post How to Serve a Party Wall Notice appeared first on White & Lloyd.

]]>
How to be a Party Wall Surveyor https://www.wlbuildingsurveyors.co.uk/2018/10/how-to-be-a-party-wall-surveyor/ Thu, 04 Oct 2018 15:43:18 +0000 http://wandl.simplecsr.com/?p=207430 What do party wall surveyors actually do and what are the skills required? With the continued growth of urban developments, exposure to the Party Wall Act is becoming ever more relevant to homeowners and construction professionals alike. Our senior party wall surveyor, Michael White, explores the skills required of the party wall surveyor and what […]

The post How to be a Party Wall Surveyor appeared first on White & Lloyd.

]]>
What do party wall surveyors actually do and what are the skills required?

With the continued growth of urban developments, exposure to the Party Wall Act is becoming ever more relevant to homeowners and construction professionals alike. Our senior party wall surveyor, Michael White, explores the skills required of the party wall surveyor and what it takes to be successful in the role…

For many years, the role of party wall surveyor has been filled by a wide range of professionals, with varying degrees of success. It is reasonably common to see an architect or structural engineer switch hats from designer to party wall surveyor when needed, which begs the question: Who is best placed to fill the role? Can a homeowner act for themselves? Is there any benefit in using a specialist party wall surveyor?

The following paragraphs discuss the skills required and the expertise needed to be successful in the role.

The definition of a Party Wall Surveyor

It seems sensible to begin with a look at what a party wall surveyor actually does. Who are they? What do they do? What skills do they have? The Act itself provides a suitably broad definition, Section 20 helpfully describes the surveyor as:

“… any person not being a party to the matter appointed or selected under section 10 to determine disputes in accordance with the procedures set out in this Act.”

It is generally accepted that “any person not being a party to the matter” includes anyone and everyone that is not the Building Owner, the Adjoining Owner, or a person with an interest in either property. So, it could be argued that anyone, other than the owner, can be the party wall surveyor…… the contractor, the architect, the engineer, the butcher, the baker, the candlestick maker….

So if anyone could do it, why don’t they?

Because it takes no small amount of skill, knowledge, competence and expertise to be effective. The successful party wall surveyor will be able to:

  1. Have a detailed understanding of the proposed works
  2. Call upon a construction knowledge to understand the implications of the work on both Building Owner and Adjoining Owner
  3. Understand the works which are notifiable under the Act
  4. Have a knowledge of the requirements of the Act in the serving of valid notices
  5. Show an understanding of the spirit of the Act
  6. Effectively resolve disputes within the requirements of section 10 of the Act

 

The skills required

There is clearly a baseline level of construction knowledge required as a starting point. The next step is to then understand the process and mechanisms contained within the Act before, finally, having the ability to apply the construction knowledge to successfully implement the requirements of the Act.

The required skills are best assessed by considering the specific tasks carried out in preparing and serving a typical award.  When acting on behalf of the Building Owner an appointed surveyor will need to:

  1. Review drawings and understand works proposed

Skills Required:

  1. Construction knowledge
  2. Ability to interpret the impact of works on adjoining properties

 

  1. Prepare and serve notice(s)

Skills Required:         

  1. Understanding of sections 1, 2, 3 and 6 and of the Act
  2. Knowledge of which areas of the work are notifiable
  3. Knowledge of which notices are required
  4. Knowledge of what is required of a valid notice
  5. Knowledge of how to retrieve Adjoining Owner details and the difference between an Adjoining Owner and an Adjoining Occupier

 

  1. Secure appointment from Building Owner(s)

Skills Required:         

  1. Commercial skills to agree level of fee (fixed fee? hourly rate?)
  2. Understanding a valid letter of appointment

 

  1. Prepare Schedule of Existing Condition

Skills Required

  1. Ability to carry out detailed inspection of adjoining property
  2. Understanding of construction types
  3. Ability to describe and record existing defects
  4. Ability to prepare formal document to be appended to the award

 

  1. Prepare draft Award

Skills Required:

  1. Knowledge of what is required from an award
  2. Ability to prepare a legally binding document, valid under the Act

 

  1. Agree terms of final award

Skills Required:

  1. Understanding of sections 7, 10, 11 and 12 of the Act
  2. Negotiation and communication skills
  3. Ability to resolve disputes within the meaning of the Act

 

  1. Prepare and serve final award documents

Skills Required:

  1. Attention to detail in co-ordinating all details into final bound document
  2. Administrative skills to record and store information

 

  1. Post award inspections, resolving issues

Skills Required:

  1. Understanding of sections 8, 10, 11 and 12 of the Act
  2. Ability to resolve disputes within the meaning of the Act
  3. Understanding of the legal process and ability to deal with an appeal process

 

It should be noted that each Award comes with a unique set of circumstances and, consequently, there is a need for an adaptable and flexible approach. The skills detailed above are generic in nature and relate to a standard award (of which there is, of course, no such thing). To be effective in the role the party wall surveyor will need to display abilities in: dispute resolution, communication, administration, knowledge of legislation and knowledge of construction.

About the author:

Michael White has been working in the construction industry for 18 years and is a Chartered Building Engineer (C.Build.E) and a fellow of the Chartered Association of Building Engineers (FCABE). He is also a member of the Faculty of Party Wall Surveyors (MFPWS) and an associate member of the Royal Institution of Chartered Surveyors (AssocRICS).

Michael has a first class honours degree in Building Surveying from the University of Reading and now practices as a Party Wall Surveyor and Building Engineer in the high end residential sector. He is one of two directors at White & Lloyd Ltd, a chartered construction consultancy based in Weybridge, Surrey.

The practice is accredited by the Chartered Institute of Building (CIOB) and offers advice on party wall matters in Fulham, Wandsworth, Battersea, Wimbledon, Surbiton, Weybridge and throughout Surrey and South West London.

We thrive on your feedback, if you have any comments or questions on the above article we would be delighted to hear from you:

Telephone: 01932 918348

E-mai: partywall@whiteandlloyd.com

Twitter: @whiteandlloyd

 

 

The post How to be a Party Wall Surveyor appeared first on White & Lloyd.

]]>
The Party Wall etc Act 1996 https://www.wlbuildingsurveyors.co.uk/2018/10/the-party-wall-etc-act-1996/ Thu, 04 Oct 2018 15:42:58 +0000 http://wandl.simplecsr.com/?p=207428 The Party Wall etc Act – Who is involved? What do they do? When do they do it? The process of resolving a dispute under The Party Wall ect Act can involve input from a myriad of people, many of which are operating at the expense of the Building Owner. Here, Michael White C.Build.E MCABE […]

The post The Party Wall etc Act 1996 appeared first on White & Lloyd.

]]>
The Party Wall etc Act – Who is involved? What do they do? When do they do it?

The process of resolving a dispute under The Party Wall ect Act can involve input from a myriad of people, many of which are operating at the expense of the Building Owner. Here, Michael White C.Build.E MCABE MFPWS, one of our senior surveyors, explains who is involved in the process, their purpose and the responsibilities of their role….

The Roles

Within the mechanism of The Party Wall ect Act, when a dispute arises between property owners, both owners develop a key role within the process. Each owner may then be represented by a surveyor and, in the interests of avoiding a stalemate, a third surveyor is duly selected.

So, at the very outset of a dispute, there is the potential for involvement from five people, and this is before we consider the roles of the designers, contractors and engineers.

The following definitions attempt to define the responsibilities of each role and, as a result, provide some insight into their involvement within the process.

  1. The Building Owner(s)

The Building Owner is the central figure of the process, it is their intention to carry out works that instigates the process by the serving of notices. There is a simple definition contained within the Act:

“Building owner” means an owner of land who is desirous of exercising rights under this Act”

The key role of the Building Owner is to serve notice and, in the case of a dispute, appoint a surveyor. All joint owners of a property are regarded as Building Owners and all should be named as such on any notices served.

  1. The Adjoining Owner(s)

The term “Adjoining Owner” covers any owner of land, buildings, storeys or rooms adjoining those of the Building Owner. Clearly the term “adjoining” requires some definition as it will vary depending on the type of work to be undertaken and the proximity between the two buildings. Under section 6 an Adjoining Owner can be an owner of buildings within 6m of the proposed work.

Section 20 contains the following definition of an Adjoining Owner:

“(a) a person in receipt of, or entitled to receive, the whole or part of the rents or profits of land;

(b) a person in possession of land, otherwise than as a mortgagee or as a tenant from year to year or for a lesser term or as a tenant at will;

(c) a purchaser of an interest in land under a contract for purchase or under an agreement for a lease, otherwise than under an agreement for a tenancy from year to year or for a lesser term;”

It can therefore be summarised that an owner is a person with a freehold or leasehold interest in the land and any tenant with a lease greater than one year. An owner does not include a mortgagee (ie: a lender with an interest).

It becomes clear that there may be two or more Adjoining Owners to any given project. If the building owner wishes to excavate along the boundary line and he lives next door to a rented property, both the landlord and tenant will be regarded as Adjoining Owners.

  1. The Building Owners Surveyor

Section 20 defines the surveyor as:

“any person not being a party to the matter appointed or selected under section 10 to determine disputes in accordance with the procedures set out in this Act.”

If a dispute has arisen the parties are required to appoint a surveyor. This can be anyone that is not a party to the matter. The surveyor does not need to have any specific qualifications and he may already be involved in the works (ie: as an architect or engineer). While qualifications are not a requirement, it is generally accepted that a party wall surveyor should have experience and competence to be able to act in the role of an expert. The surveyor should at least be able to make basic judgments on the substantive issues without having to seek advice from other professionals.

  1. The Adjoining Owners Surveyor

The surveyor acting on behalf of the Adjoining Owner. As with the Building Owner’s surveyor, this person can be anybody not involved in the dispute.

The role of the Adjoining Owners Surveyor is primarily to represent the interests of the Adjoining Owner and ensure the correct implementation of the requirements of the Act. Key responsibilities include:

  • Review and comment on the notices, with the intention of verifying their validity
  • Cooperate in the forthwith selection of the Third Surveyor
  • Ensure a Schedule a Conditions is carried out properly (not a requirement under the Act but generally considered as good practise)
  • Review draft award documents and provide comments to ensure fair and comprehensive award(s) are served
  • Countersign awards, document registers and schedules of condition

The Adjoining Owners surveyor will usually allow time within his fee to carry out a site inspection during the works and after completion. The purpose of these visits is to ensure work is progressing in accordance with the drawings and method statements and, after completion, to review the adjoining property against the schedule of condition and check for damage caused.

  1. The Third Surveyor

In instances where there are two surveyors appointed (one acting for the Building Owner and one acting for the Adjoining Owner) the first act they must undertake in resolving the dispute is to select a Third Surveyor. The usual process is that the Building Owners surveyor nominates three choices to the Adjoining Owners surveyor, who then proceeds to select their preferred option. If the Adjoining Owners surveyor does not feel any of the three choices are suitable they may decline to select any of them and suggest three alternatives. In instances where the two surveyors are unable to agree on the selection of the Third Surveyor they must refer it to the Appointed Officer within the local authority to make the selection.

The Third Surveyor does not need to agree to be selected and, often, he will not even be aware of his selection until called upon.

The Third Surveyor is usually an experienced specialist in party wall matters.

  1. The Agreed Surveyor

When an Adjoining Owner indicates their dissent, they are then required to appoint a surveyor. They may appoint the same surveyor as the Building Owner, in which case the surveyor in question becomes the Agreed Surveyor and prepares the award on behalf of both parties. In this instance, there is no requirement for a Third Surveyor.

  1. Design Engineers

This term covers the structural engineer (or group of engineers) that produced the engineering elements of the proposed design. In most projects a set of engineering details (drawings and calculations) are needed at the time notices are served as they set out the extent of the notifiable works and detail numbers, sizes and locations of steel beams. The structural design is also likely to set out the depth and location of foundations, so the details prescribe the depth of excavations and are crucial to notices served under section 6.

The role of the design engineers becomes even more prevalent on basement projects, where the design is far more involved and includes the temporary works (propping and temporary support details), reinforced concrete underpinning and retaining walls. The technical details of such a design may extend beyond the expertise of most surveyors, in which case it is prudent to engage the services of a checking engineer to assist in the evaluation of the design.

  1. Checking Engineers

A dispute may involve complex construction issues and the surveyors may need to rely on input from experts in order to reach the correct solution. On complex engineering projects most Adjoining Owners Surveyors will appoint a third party engineer to assess the design and comment on its adequacy. Checking engineers may also be requested to visit the site during the works to assess conditions on site as work progresses or to ensure construction methods are being followed.

The cost of the checking engineers fees are usually written into the award and, as with the vast majority of costs uncured under the Act, are to be paid by the Building Owner.

  1. Contractors

The building firm selected to carry out the proposed works. They may be requested to provide information on how they intend to carry out works, the programme of works, method statements, insurances…etc.

  1. Architects

The person or practice responsible for the design of the proposed works. The architect is usually the person with the most knowledge of a proposed scheme and has normally been involved since the projects conception and through the planning stages. They are responsible for deciding design information and would need to produce drawings to show detail around the notifiable works. This normally involves weathering or waterproofing detail, lead flashings cut in to the party wall…etc.

  1. Adjoining Occupier

A person, other than the Adjoining Owner, that resides at an Adjoining Owner’s property. Occupiers have limited rights and obligations and a Building Owner is not required to serve an Occupier with a notice of intended works. However, if the building owner wishes to carry out works by consent, he needs to have the consent of the adjoining occupiers as well as the adjoining owners (section 3(3)(a)).

Adjoining occupiers are obliged to allow entry under section 8 of the Act, subject to the requirements of notice in that section, and can commit an offence if they do not permit entry.

  1. Appointed Officer

Section 10(8) covers circumstances where two surveyors are appointed to resolve a dispute but fail to agree on the selection of the Third Surveyor (a simple task that should be carried out with ease but, sadly, can sometimes prove to be the first sticking point between two surveyors). In such a case section 10(8) comes into play and the Appointed Officer is troubled for his view.

The Appointed Officer is defined within the Act as:

“the person appointed under this Act by the local authority to make such appointments as are required under section 10(8)”

The local authority are expected to have fulfilled their responsibility to have appointed such an officer but, in reality, they are usually unclear as to this requirement. The duty would normally fall to the Head of Building Control or someone with a similar construction related mindset.

It is worth pointing out that, if the two surveyors appointed cannot agree on the simple point of selecting a third surveyor, it does not bode well for the future possibilities of resolving the intricacies of the dispute in question. In such an instance it may be sensible to refer the issue to the Third Surveyor at an early stage in the process.

 

We thrive on your feedback, if you have any comments or questions on the above article we would be delighted to hear from you:

Telephone: 01932 918348

E-mail: partywall@whiteandlloyd.com

Twitter: @whiteandlloyd

About the author:

Michael White has been working in the construction industry for 18 years and is a Chartered Building Engineer (C.Build.E) and member of the Chartered Association of Building Engineers (MCABE). He is also a member of the Faculty of Party Wall Surveyors (MFPWS) and an associate member of the Royal Institution of Chartered Surveyors (AssocRICS).

Michael has a first class honours degree in Building Surveying from the University of Reading and now practices as a Party Wall Surveyor and Building Engineer in the high end residential sector. He is one of two directors at White & Lloyd Ltd, a chartered construction consultancy based in Weybridge, Surrey.

The practice is accredited by the Chartered Institute of Building (CIOB) and offers advice on party wall matters in Fulham, Chelsea, Clapham, Kensington, Wimbledon and throughout South West London.

 

 

The post The Party Wall etc Act 1996 appeared first on White & Lloyd.

]]>
The Party Wall etc Act 1996- A Beginners Guide https://www.wlbuildingsurveyors.co.uk/2018/09/the-party-wall-etc-act-1996-a-beginners-guide/ Thu, 13 Sep 2018 19:04:58 +0000 http://wandl.simplecsr.com/?p=207262 The post The Party Wall etc Act 1996- A Beginners Guide appeared first on White & Lloyd.

]]>

The Party Wall Act – A Beginners Guide

Michael White C.Build.E FCABE FFPWS, one of our senior surveyors, offers his “beginners guide”.

The Party Wall Act 1996- A Beginners Guide

We appreciate that many people wishing to carry out works on their property have the requirements of The Party Wall Act thrust upon at a relatively late stage in the pre-construction process. We also understand it can be a daunting process for those that have not experienced it before. Here, Michael White C.Build.E MCABE MFPWS, one of our senior surveyors, offers his “beginners guide” which aims to provide an outline understanding of party walls and the requirements of the Party Wall Act…

What is the Party Wall Act?

The Party Wall etc Act 1996 provides a procedure to follow when building work involves a party wall or party fence wall, some excavations close to neighbouring buildings, and new walls at boundaries. The Act permits owners to carry out certain specific works, including work to the full thickness of a party wall, whilst at the same time protecting the interests of anyone else who might be affected by that work. The Act is designed to avoid or minimise disputes by making sure property owners notify their neighbours in advance of certain proposed works.

The Act provides a mechanism for resolving disputes and enabling works to proceed. It also requires that, where the adjoining owner does not ‘agree’ in writing to the works, a surveyor or surveyors will determine the time and way in which those works are carried out.

What is a party wall?

Party walls usually separate buildings belonging to different owners but could include garden walls built astride a boundary – known as party fence walls. Where a wall separates two different size buildings often only the part that is used by both properties is a party wall, the rest belongs to the person or persons on whose land it stands.

The “etc” within The Party Wall etc Act 1996 is so included because the provisions of the Act are not limited to party walls, they also include party structures and party fence walls.

Section 20 of the Act defines each:

“party fence wall” means a wall (not being part of a building) which stands on lands of different owners and is used or constructed to be used for separating such adjoining lands, but does not include a wall constructed on the land of one owner the artificially formed support of which projects into the land of another owner;

“party structure” means a party wall and also a floor partition or other structure separating buildings or parts of buildings approached solely by separate staircases or separate entrances;

What is covered by the Act?

There are certain items of work that you can only be done after notifying the adjoining owners and either receiving written agreement of the neighbour or with a Party Wall Award prepared by a surveyor/s.

Notifiable works include (but are not limited to):

  • cutting into a wall to take the bearing of a beam, for example for a loft conversion
  • inserting a damp proof course, even if only to your own side of a party wall
  • raising a party wall and, if necessary, cutting off any objects preventing this from happening
  • demolishing and rebuilding a party wall
  • underpinning a party wall or part of a party wall
  • weathering the junction of adjoining walls or buildings by cutting a flashing into an adjoining building
  • excavating foundations within three metres of a neighbour’s structure and lower than its foundations
  • excavating foundations within six metres of a neighbour’s structure and below a line drawn down at 45° from the bottom of its foundations.

Notices are also required if it is proposed to build a new wall on the line of junction (boundary line). A party wall surveyor will usually be able to confirm which work is notifiable and advice the notice period and type of notice required.

What is not covered by the Act?

The Act relates only to certain specific types of work and is permissive in nature. It should not be seen as a method of objecting to or preventing works and it is not intended to be applied to minor jobs that do not affect the structural integrity or loading of a party wall.

It is generally agreed that works such as fixing plug sockets, screwing in shelving or replastering walls are minor works and do not require a notice.

Notices

The workings of the Act are always instigated by the of issuing notices. This is the first stage of the process and, without the issue of valid notices, no further action can be taken under the provision of the Act.

Written notice must be served on adjoining owners at least two months before starting any party wall works (one month for works to the line of junction or excavations). All adjoining owners must be served a notice and there are likely to be instances where there is more than one adjoining property and more than one owner of each property (ie: if the adjoining property is split into flats and owned on a leasehold basis, notices will be required to both leaseholder and freeholder of all flats affected by the works). Works to a party wall, or those affecting a ceiling or floor, will also require a notice to adjoining owners living above or below.

Valid notices must contain the following information as a minimum:

  • The name and address of the building owner;
  • The nature and particulars of the proposed work including plans, sections and details of construction methods
  • The date on which the proposed work will begin.

It is essential to include the correct details on a notice as, if they are deemed invalid, then any subsequent actions are also invalid.

Responses To Notices

On receipt of a notice, an adjoining owner has three possible courses of action:

  1. To consent to the works going ahead as described. A consenting Adjoining Owner retains all rights under the Act including the right to appoint a surveyor later in the process if there is a dispute at that stage.
  2. To dissent and appoint a surveyor. The Act allows the Owners to concur in the appointment of a single ‘Agreed’ surveyor or appoint their own separate surveyor.
  3. Issue a counter notice to set out certain conditions required for the benefit of the Adjoining Owner. The Counter Notice should set out what additional or modified work the Adjoining Owner would like to be included for his benefit

In most cases, if the adjoining does not respond within 14 days then a deemed dispute is said to have occurred and the person carrying out the work must appoint a surveyor to act on the adjoining owners behalf.

If adjoining owners provide written consent to the works as set out within the notices, then there is no dispute to resolve and no further need for party wall surveyors or, indeed, the Party Wall Act. Assuming work proceeds as detailed within the notice and no damage is caused, then no further involvement is necessary.

Resolving Disputes

If adjoining owners dissent to the works (or if no response is received and a deemed dissent has arisen) then a dispute has occurred which must be resolved under the requirements of Section 10 of The Act. It is worth reiterating that the Act is one of enablement, it is not there to prevent works from taking place and it offers a route to end disputes at every stage. Where written agreement is not given, the solution the Act provides is for both parties to appoint an ‘agreed surveyor’ who will act impartially or for each owner to appoint a surveyor who in turn appoint a third surveyor. The surveyors then work together to agree the terms under which work may proceed. The surveyor(s) will review the plans, notices and structural details of the works and, after considering the impact of the works, will draw up an agreement which sets out the terms under which work can be carried out (the Award).

The Party Wall Award

The award will usually record the condition of the relevant part of adjoining property before work begins (this is not a requirement under the Act but is considered good practice and is duly provided by most good surveyors). The award may also grant access to both properties so that the works can be safely carried out and the surveyor/s can inspect work in progress.

Generally, the building owner who started the work pays for all expenses of work and the reasonable costs incurred by all parties as a result, this will include the surveyors fees for both Building Owner and Adjoining Owner.

We thrive on your feedback, if you have any comments or questions on the above article we would be delighted to hear from you:

Telephone: 01932 918348

E-mai: partywall@whiteandlloyd.com

Twitter: @whiteandlloyd

About the author:

Michael has been working in the construction industry for 18 years. He has a first class honours degree in Building Surveying from the University of Reading and now practices as a Party Wall Surveyor and Building Engineer in the high end residential sector.

Michael is a Chartered Building Engineer (C.Build.E) and member of the Chartered Association of Building Engineers (MCABE). He is also a member of the Faculty of Party Wall Surveyors (MFPWS) and an associate member of the Royal Institution of Chartered Surveyors (AssocRICS).

Michael is one of two directors at White & Lloyd Ltd, a chartered construction consultancy based in

Weybridge, Surrey. The practice is accredited by the Chartered Institute of Building (CIOB).

Are you a Building Owner?

If you are planning on doing some work to your property here are some of the things you need to know before you get started.

Are you an Adjoining Owner?

If your neighbours are planning on doing some work here are some of the things you need to know.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post The Party Wall etc Act 1996- A Beginners Guide appeared first on White & Lloyd.

]]>