Ask Mike From White & Lloyd Questions about Party Wall Agreements. https://www.wlbuildingsurveyors.co.uk/category/ask-mike/ Building Surveyors Thu, 12 Dec 2019 13:58:09 +0000 en-GB hourly 1 https://wordpress.org/?v=6.1.7 https://www.wlbuildingsurveyors.co.uk/wp-content/uploads/2019/12/cropped-favicon-32x32.png Ask Mike From White & Lloyd Questions about Party Wall Agreements. https://www.wlbuildingsurveyors.co.uk/category/ask-mike/ 32 32 How Much Does a Party Wall Agreement Cost? https://www.wlbuildingsurveyors.co.uk/2019/06/how-much-is-a-party-wall-agreement/ Thu, 06 Jun 2019 10:01:49 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208256 The post How Much Does a Party Wall Agreement Cost? appeared first on White & Lloyd.

]]>

How Much Does a Party Wall Agreement cost?

The cost of a party wall agreement will depend on the type of project being carried out and the quality of the design information in place. The cost is determined by the surveyors hourly rate and the amount of time they are required to spend to put the awards in place. Most party wall surveyors charge a fixed hourly rate for all party wall matters, this will typically range from £120 – £250 per hour.

THE EXPECTED HOURS AND COSTS FOR A PARTY WALL AGREEMENT WOULD BE:

TWO APPOINTED SURVEYORS
Project Type Building Owners SurveyorAdjoining Owners SurveyorTotal Cost
(per agreement)
Loft Conversion6 to 8 hours
£900 to £1200
6 to 8 hours
£900 to £1200
£1800 to £2400
Extension8 to 10 hours
£1200 to £1500
8 to 10 hours
£1200 to £1500
£2400 to £3000
New Build10 to 12 hours
£1500 to £1800
10 to 12 hours
£1500 to £1800
£3000 to £3600
Basement12 to 18 hours
£1800 to £2700
12 to 18 hours
£1800 to £2700
£3600 to £5400

Assumes an hourly rate of £150 per hour.

AGREED SURVEYOR
Project Type Agreed SurveyorTotal Cost
(per agreement)
Loft Conversion6 to 8 hours
£900 to £1200
Extension8 to 10 hours

£1200 to £1500
New Build10 to 12 hours

£1500 to £1800
Basement12 to 18 hours
£1800 to £2700

Assumes an hourly rate of £150 per hour.

The number of hours involved will depend on:
  1. The quality and completeness of the design information
  2. The complexity of the project
  3. The level of risk of damage on the adjoining property
  4. The quality and completeness of the draft award and schedule of condition prepared by the building owners surveyor
  5. Whether a matter has had to be referred to the Third Surveyor

It should be noted that there is no upper limit on the costs, as long as fees are reasonable.

Once the awards are agreed the surveyors will apportion the “reasonable” fees. In usual circumstances fees will be payable by the building owner.

WHAT IF SURVEYORS FEES ARE NOT REASONABLE?
It falls to the building owners surveyor to determine whether or not the adjoining owners surveyors fees are reasonable. If there is concern then surveyors will review timesheets and ensure that all time spent is within the surveyors remit and in direct relation to the work being carried out.

If there is concern over the fees then the matter may be referred to the third surveyor for a determination.

If an award is served containing unreasonable fees then it may be appealed, in the County Court, within 14 days of being served.

This action can incur additional cost, we always recommend that specialist advice is sought before referring a matter to the third surveyor or appealing an award.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post How Much Does a Party Wall Agreement Cost? appeared first on White & Lloyd.

]]>
How To Reduce Party Wall Costs https://www.wlbuildingsurveyors.co.uk/2019/06/how-to-reduce-party-wall-costs/ Thu, 06 Jun 2019 09:38:26 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208245 The post How To Reduce Party Wall Costs appeared first on White & Lloyd.

]]>

How To Reduce Party Wall Costs

The cost of a party wall agreement will depend on the type of project being carried out, the quality of the design information in place and the number of surveyors involved. The cost is determined by the surveyors hourly rate and the amount of time they are required to spend to put the awards in place. The cost of the party wall process will be reduced if surveyors hours can be kept to a minimum.

How To Reduce Party Wall Costs

DISCUSS THE WORKS WITH THE ADJOINING OWNERS BEFORE SERVING NOTICE:

The easiest, quickest and cheapest way to reach a party wall agreement is to receive the consent of the adjoining owners.

If a notice has been served, and the adjoining owners provide a written consent, then this is the end of the process.

We strongly recommend that building owners discuss their works with the adjoining owners, outlining the specific aspects that may affect them.

Adjoining owners are far more likely to consent if they understand the works and the reason for serving notice.

It is worth bearing in mind that the two parties (building owner and adjoining owner) are free to reach any agreement they want. It is perfectly valid for an adjoining owner to consent on the basis that the building owners provides something in return. 

This could be:

  • A survey of the adjoining property
  • A promise to repair the fence
  • A bottle of wine
  • A future consent to future work by the adjoining owner
  • Anything that both parties decide
USE AN AGREED SURVEYOR WHERE POSSIBLE
Less complex jobs are most efficiently dealt with by an agreed surveyor (where one surveyor acts for both parties). This route needs the agreement of all parties (both property owners and the surveyor in question) but it usually represents the quickest and most cost effective means of putting a party wall agreement in place.

The agreed surveyor route means the building owner is liable for one set of fees rather than two, so it is worth discussing with the adjoining owner to see if this is a viable option.

APPOINT A COMPETENT DESIGN TEAM
It is worth checking the competency and experience of the design team before appointing them. Incomplete or poorly considered designs can delay the party wall process and add a significant cost.

Competent architects and engineers should be aware of the information that is required for the party wall agreement. If there is any doubt then you should pass the design information to a party wall surveyor for comments on its adequacy before starting the party wall process.

APPOINT A COMPETENT PARTY WALL SURVEYOR

Costs will be higher if the adjoining owners surveyor is spending significant amounts of time correcting mistakes or poorly presented information form the building owners surveyor.

The building owners surveyor is usually responsible for:

  1. Preparing and sending notices
  2. Preparing the schedule of condition
  3. Preparing the draft award
  4. Reviewing design information before sending on
  5. Preparing the document register

If the one surveyor is spending time correcting mistakes made by the other then costs will be higher.

It is therefore worth checking the accreditation and experience of a surveyor before appointing them.

Do not be put off by a higher hourly rate. This will usually signify greater competency and experience so the process should go through quicker and smoother, meaning a lower total cost.

BE PREPARED TO COMPROMISE
A party wall agreement often turns into a negotiation, whereby the adjoining owners may have specific concerns they would like addressed (often revolving around hours of work, location of scaffolding, the use of protective hoarding…etc).

Often the cost of enforcing a particular point can outweigh the cost of agreeing to it, so a flexible and conciliatory approach can be an effective way of minimising costs.

WHAT IF SURVEYORS FEES ARE NOT REASONABLE?
It falls to the building owners surveyor to determine whether or not the adjoining owners surveyors fees are reasonable. If there is concern then surveyors will review timesheets and ensure that all time spent is within the surveyors remit and in direct relation to the work being carried out.

If there is concern over the fees then the matter may be referred to the third surveyor for a determination.

If an award is served containing unreasonable fees then it may be appealed, in the County Court, within 14 days of being served.

This action can incur additional cost and we always recommend that specialist advice is sought before referring a matter to the third surveyor or appealing an award.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post How To Reduce Party Wall Costs appeared first on White & Lloyd.

]]>
Party Wall Surveying London: All You Need To Know https://www.wlbuildingsurveyors.co.uk/2019/03/party-wall-surveyor-london/ Tue, 19 Mar 2019 18:00:36 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208167 The post Party Wall Surveying London: All You Need To Know appeared first on White & Lloyd.

]]>

Party Wall Surveying Surrey:

All You Need To Know

We appreciate people carrying out building works in London have the requirements of The Party Wall Act thrust upon them. We also understand it can be a daunting process for those that have not experienced it before.

We are party wall surveyors in London, Surrey and we have recently worked to resolve party wall disputes in Fulham, Putney, Battersea and Clapham. We are pleased to provide a local and relevant  explanation of party walls and The Party Wall Act.

What is a party wall?

Party walls are usually walls built on the land of two owners. They separate buildings belonging to different owners and could also include garden walls built astride a boundary – known as party fence walls.

Party Walls in South West London are most commonly found separating the Victorian terraced housing.  The owners on both sides of the wall have rights over it, this is why The Party Wall Act exists.

What is a party wall act?

The Party Wall etc Act 1996 provides a procedure to follow when building work is likely to affect neighbouring properties. The Act enables owners to carry out works to a party wall, whilst at the same time protecting the interests of anyone else who might be affected by that work. The Act is designed to avoid or minimise disputes by making sure property owners notify their neighbours in advance of certain proposed works.

The Act provides a mechanism for resolving disputes and enabling works to proceed. It also requires that, where the adjoining owner does not ‘agree’ in writing to the works, a surveyor or surveyors will determine the time and way in which those works are carried out

What is covered by the Act? ?
The Party Wall Act sets out certain items of work that can only be done after notifying the adjoining owners and either receiving written agreement of the neighbour or with a Party Wall Award prepared by a surveyor.
Notifiable works include (but are not limited to):

  • Cutting into a wall to take the bearing of a beam, for example for a loft conversion
  • Inserting a damp proof course, even if only to your own side of a party wall
  • Raising a party wall and, if necessary, cutting off any objects preventing this from happening
  • Demolishing and rebuilding a party wall
  • Underpinning a party wall or part of a party wall
  • Weathering the junction of adjoining walls or buildings by cutting a flashing into an adjoining building
  • Excavating foundations within three metres of a neighbour’s structure and lower than its foundations
  • Excavating foundations within six metres of a neighbour’s structure and below a line drawn down at 45° from the bottom of its foundations.
  • Notices are also required if it is proposed to build a new wall on the line of junction (boundary line). Our surveyors will be happy to confirm which work is notifiable and advice the notice period and type of notice required.
Work Not Covered By The Act?
The Party Wall Act is not intended to be applied to minor jobs that do not affect the structural integrity or loading of a party wall.

It is generally agreed that works such as fixing plug sockets, screwing in shelving or replastering walls are minor works and do not require a notice. If you are in London, and you have any doubt if your works require a notice to be served, please speak to our surveyors.

Notices
The workings of the Act are always instigated by the of issuing notices.

Written notice must be served on adjoining owners at least two months before starting any party wall works (one month for works to the line of junction or excavations). All adjoining owners must be served a notice and there are likely to be instances where there is more than one adjoining property and more than one owner of each. Works to a party wall, or those affecting a ceiling or floor, will also require a notice to adjoining owners living above or below.

It is essential to include the correct details on a notice as, if they are deemed invalid, then any subsequent actions are also invalid. Our surveyors are experienced at serving notices in London and Surrey. Please contact our Fulham office or our Thames Ditton office if you need any help.

Where written agreement is not given, the solution the Act provides is for both parties to appoint a surveyor. The surveyors then work together to agree the terms under which work may proceed. The surveyor(s) will review the plans, notices and structural details of the works and, after considering the impact of the works, will draw up an agreement which sets out the terms under which work can be carried out (the Award).

Responses To Notices
On receipt of a notice, an adjoining owner has three possible courses of action:

  1. To consent to the works going ahead as described. A consenting Adjoining Owner retains all rights under the Act including the right to appoint a surveyor later in the process if there is a dispute at that stage.
  2. To dissent and appoint a surveyor. The Act allows the Owners to concur in the appointment of a single ‘Agreed’ surveyor or appoint their own separate surveyor.
  3. Issue a counter notice to set out certain conditions required for the benefit of the Adjoining Owner. The Counter Notice should set out what additional or modified work the Adjoining Owner would like to be included for his benefit

In most cases, if the adjoining does not respond within 14 days then a deemed dispute is said to have occurred and the person carrying out the work must appoint a surveyor to act on the adjoining owners behalf.
If adjoining owners provide written consent to the works as set out within the notices, then there is no dispute to resolve and no further need for party wall surveyors. Assuming work proceeds as detailed within the notice and no damage is caused, then no further involvement is necessary.

Resolving Disputes
If adjoining owners dissent to the works then a dispute has occurred which must be resolved to allow works to proceed. It is worth reiterating that the Act is one of enablement, it is not there to prevent works from taking place and it offers a route to end disputes at every stage.

Where written agreement is not given, the solution the Act provides is for both parties to appoint a surveyor. The surveyors then work together to agree the terms under which work may proceed. The surveyor(s) will review the plans, notices and structural details of the works and, after considering the impact of the works, will draw up an agreement which sets out the terms under which work can be carried out (the Award).

The Party Wall Award
The award will usually record the condition of the relevant part of adjoining property before work begins (this is not a requirement under the Act but is considered good practice and is duly provided by most good surveyors). This survey of the adjoining properties is particularly important in London where there are often several properties in close proximity, and therefore a higher chance of works affecting neighbours.

The award may also grant access to both properties so that the works can be safely carried out and the surveyor/s can inspect work in progress.

Generally, the building owner who started the work pays for all expenses of work and the reasonable costs incurred by all parties as a result, this will include the surveyors fees for both Building Owner and Adjoining Owner.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post Party Wall Surveying London: All You Need To Know appeared first on White & Lloyd.

]]>
Can My Neighbour Build On A Boundary Wall? https://www.wlbuildingsurveyors.co.uk/2019/03/can-my-neighour-build-on-a-boundary-wall/ Tue, 19 Mar 2019 16:58:55 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208160 The post Can My Neighbour Build On A Boundary Wall? appeared first on White & Lloyd.

]]>

Party Wall Surveying Surrey:

All You Need To Know

We appreciate people carrying out building works in Surrey have the requirements of The Party Wall Act thrust upon them. We also understand it can be a daunting process for those that have not experienced it before.

We are party wall surveyors in Thames Ditton, Surrey and we have recently worked to resolve party wall disputes in Esher, Kingston, Weybridge and Guildford. We are pleased to provide a local and relevant  explanation of party walls and The Party Wall Act.

What is a party wall?

Party walls are usually walls built on the land of two owners. They separate buildings belonging to different owners and could also include garden walls built astride a boundary – known as party fence walls.

Can My Neighbour Build On A Boundary Wall?

The short answer is “yes, subject to serving a valid notice and following the processes set out in The Party Wall Act.
Boundary walls are referred to in the Act as “Party Fence Walls”. The definition set out for a party fence wall is:

“a wall (not being part of a building) which stands on lands of different owners and is used or constructed to be used for separating such adjoining lands”

The party wall act only applies to “structures” (ie: a wall with a foundation), it does not apply to timber fences or other screens.

What Rights Does My Neighbour Have?

Section 2 of the Act provides the following rights to people wishing to alter a boundary wall:

  • To underpin, thicken or raise a party fence wall
  • To make good, repair, or demolish and rebuild, a party fence wall in a case where such work is necessary on account of defect or want of repair of the structure or wall
  • To demolish a party structure which is of insufficient strength or height for the purposes of any intended building and to rebuild it of sufficient strength or height for the said purposes (including rebuilding to a lesser height or thickness where the rebuilt structure is of sufficient strength and height for the purposes of any adjoining owner)
  • To cut into a party structure for any purpose (which may be or include the purpose of inserting a damp proof course)
  • To cut away any footing or any projection in order to erect, raise or underpin any such wall or for any other purpose
  • To cut away or demolish parts of any wall or building overhanging the land of the building owner, to enable a vertical wall to be erected or raised
  • To raise a party fence wall or to demolish and rebuild a party fence wall
  • Before carrying out this work, the person wishing to do so (known as the building owner) must serve a valid notice to clearly set out what they intend to do.
Notices

The workings of the Act are always instigated by the of issuing notices.

Written notice must be served on adjoining owners at least two months before starting any party wall works (one month for works to the line of junction or excavations). All adjoining owners must be served a notice and there are likely to be instances where there is more than one adjoining property and more than one owner of each. Works to a party wall, or those affecting a ceiling or floor, will also require a notice to adjoining owners living above or below.

It is essential to include the correct details on a notice as, if they are deemed invalid, then any subsequent actions are also invalid. Our surveyors are experienced at serving notices in London and Surrey. Please contact our Fulham office or our Thames Ditton office if you need any help.

Resolving Disputes

If adjoining owners dissent to the works then a dispute has occurred which must be resolved to allow works to proceed. It is worth reiterating that the Act is one of enablement, it is not there to prevent works from taking place and it offers a route to end disputes at every stage.

Where written agreement is not given, the solution the Act provides is for both parties to appoint a surveyor. The surveyors then work together to agree the terms under which work may proceed. The surveyor(s) will review the plans, notices and structural details of the works and, after considering the impact of the works, will draw up an agreement which sets out the terms under which work can be carried out (the Award).

The Party Wall Award

The award will usually record the condition of the relevant part of adjoining property before work begins (this is not a requirement under the Act but is considered good practice and is duly provided by most good surveyors).

The award may also grant access to both properties so that the works can be safely carried out and the surveyor/s can inspect work in progress.

Generally, the building owner who started the work pays for all expenses of work and the reasonable costs incurred by all parties as a result, this will include the surveyors fees for both Building Owner and Adjoining Owner.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post Can My Neighbour Build On A Boundary Wall? appeared first on White & Lloyd.

]]>
How To Get A Party Wall Agreement? https://www.wlbuildingsurveyors.co.uk/2019/03/how-to-get-a-party-wall-agreement/ Thu, 14 Mar 2019 11:28:37 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208109 The post How To Get A Party Wall Agreement? appeared first on White & Lloyd.

]]>

Before carrying out any work notifiable under The Party Wall Act, the building owner must obtain either:

a)     The consent of the adjoining owners, or:

b)     An award (agreement) that sets out the terms under which work can commence.

How To Get A Party Wall Agreement?

On receipt of notices, the adjoining owners have three responses available to them:

  1. Provide consent to the works (no further action necessary)
  2. Dissent to the works (a dispute arises and surveyors are appointed on both sides)
  3. Provide no response at all (in which case a deemed dissent arises, and a surveyor is appointed on behalf of the adjoining owner).

In option 1, if a written consent is received. Then this is considered an agreement and no further action is necessary.

In options 2 & 3, a dispute has arisen. Surveyors are appointed to resolve the dispute and serve an award. This award is often referred to as a party wall agreement as it sets the rights and responsibilities of both

The following article sets out how to get a party wall agreement.

The Process 

If you are a building owner wishing to carry out work, you will need to:

  1. Serve a party wall notice on the adjoining owners affected by the works.
  2. If the adjoining owners consent, then there is no dispute and works can commence once the notice period has run (or sooner if the adjoining owners agree)
  3. If the adjoining owners dissent then there is a dispute which needs to be resolved by surveyors.
  4. Both sides should appoint a surveyor (you can concur on the appointment of a single surveyor if both sides agree).
  5. The two surveyors (or single agreed surveyor) will then consider the works and prepare an award. The award is the agreement that sets out the rights and responsibilities of both parties. It also sets out the terms under which work can proceed.
  6. Once the award is in place then works can commence once the notice period has run.

How to get consent?

The easiest, quickest and cheapest way to reach a party wall agreement is to receive the consent of the adjoining owners.

If a notice has been served, and the adjoining owners provide a written consent, then this is the end of the process.

We strongly recommend that building owners discuss their works with the adjoining owners, outlining the specific aspects that may affect them.

Adjoining owners are far more likely to consent if they understand the works and the reason for serving notice.

It is worth bearing in mind that the two parties (building owner and adjoining owner) are free to reach any agreement they want. It is perfectly valid for an adjoining owner to consent on the basis that the building owners provides something in return. This could be:

  1. A survey of the adjoining property
  2. A promise to repair the fence
  3. A bottle of wine
  4. A future consent to future work by the adjoining owner
  5. Anything that both parties decide

What happens if the neighbour dissents? 

If the adjoining owners dissent to the notice then a “dispute” has arisen in the eyes of the Party Wall Act.

Both parties must appoint a surveyor. The surveyors will check the building plans and discuss any important points with you.

Under The Act, surveyors are required to be impartial, they are working in the best interests of the wall.

The adjoining owners property will be inspected by the surveyor(s) and its existing condition recorded. Should any damage occur during or after the work, the Schedule of Existing Condition is used to prove it is as a result of the works.

The surveyor(s) will then agree the terms under which work can begin. They will also set out any precautions that might need to be taken to protect the adjoining properties.

These terms form the Party Wall Award, a legally binding document which is signed the surveyor(s) and issued to the property owner and the adjoining owner.

The properties are then inspected on completion to check for any damage. If there is damage, then the surveyors will agree how it gets resolved.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post How To Get A Party Wall Agreement? appeared first on White & Lloyd.

]]>
Who Pays For A Party Wall Surveyor? https://www.wlbuildingsurveyors.co.uk/2019/03/who-pays-for-a-party-wall-surveyor/ Thu, 14 Mar 2019 10:37:38 +0000 https://www.wlbuildingsurveyors.co.uk/?p=208093 The post Who Pays For A Party Wall Surveyor? appeared first on White & Lloyd.

]]>

The Party Wall Act Is Instigated By The Serving Of Notices. If A Dispute Arises Then Both Parties Must Appoint A Surveyor. The Question We Are Asked Most Often Is:

Who Pays For A Party Wall Surveyor?

It is the responsibility of the building owner (the person carrying out the work) to serve notice on the adjoining owners prior to works taking place.

The adjoining owners then have three responses available to them:

 

  1. Provide consent to the works (no further action necessary)
  2. Dissent to the works (a dispute arises and surveyors are appointed on both sides)
  3. Provide no response at all (in which case a deemed dissent arises, and a surveyor is appointed on behalf of the adjoining owner).In option 1, no surveyors fees are incurred and works can commence as soon as the notice period has run.In options 2 & 3, surveyors are appointed to resolve the dispute and serve an award. Their input will incur fees – often in excess of four figures.So, who is responsible for paying those fees?

In usual circumstances 

It is the building owner that is carrying out the works and instigating the party wall process (by the serving of notices). It is, therefore, the building owner that is usually responsible for paying the surveyors fees for both sides.

What if the fees are not reasonable?

If the building owner feels the fees are not reasonable, there is a right to refer the matter to the Third Surveyor or appeal the award in the County Court (within 14 days of the award being served).

It is usually best to discuss fees with your surveyor in the first instance as they should be able to provide their timesheets as well as the timesheets for the other surveyor.

If surveyors are able to demonstrate their fees as reasonable then an appeal or Third Surveyor is unlikely to be successful.

See article How Much is a Party Wall Agreement?

When could the adjoining owner be Liable for fees? 

As a general rule, it is the person “desirous of carrying out the work” that will be liable for the fees, so usually the building owner.

The adjoining owner may become liable for fees in the following circumstances:

  1. If they are asking the building owner to carry out work over and above what they intended to (ie: to build a party wall higher or out of different materials)
  2. If they instruct their party wall surveyor on matters outside of the party wall act. The building owner is only liable for the surveyors fees within their remit as a party wall surveyor and in direct relation to the building owners works
  3. If they (or their surveyor) refers a matter to the Third Surveyor and the Third Surveyor finds in favour of the building owner. The Third Surveyor will apportion costs as they see reasonable – usually to the party they find against. If the Third Surveyor determines against the adjoining owners then they are likely to apportion their fees and any other associated costs to the adjoining owners.

We are party wall specialists

We are party wall specialists with over 15 years experience in the industry. We are based in Thames Ditton, Surrey and operate throughout Surrey and South West London.

We hope this has been useful. If you have any questions please contact us at: partywall@whiteandlloyd.co.uk

Send us a Message

Head Office

Devon House
11 High Street
Thames Ditton, Surrey
KT7 0SD
0208 191 7747

office@whiteandlloyd.com

London Office

Chester house
81-83 Fulham High Street
Fulham Green, Fulham
SW6 3JA
0203 637 2213

The post Who Pays For A Party Wall Surveyor? appeared first on White & Lloyd.

]]>